Question: Your project is using complex, unproven technology. Your team conducted a brainstorming session to identify risks. Poor allocation of project resources was the number one
Your project is using complex, unproven technology. Your team conducted a brainstorming session to identify risks. Poor allocation of project resources was the number one risk. This risk was placed on the risk register, which included at this point a
Question options:
A
Watch list
B
Potential risk response
C
Known unknown
D
List of other risks requiring additional analysis