Question: Your project performance review shows that your project's current planned value = 30,000 Euro and earned value = 29,000 Euro. Which of the following statements

Your project performance review shows that your
Your project performance review shows that your project's current planned value = 30,000 Euro and earned value = 29,000 Euro. Which of the following statements is true about your project? Select one: O a. CPI = 0.96 O b. The project is ahead of schedule O c The project has a positive cost variance O d. The project is behind schedule