Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information
Question:
Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and budgeted cost of each activity.
Baseline
Activity Name | Start (Baseline) | Finish (Baseline) | Cost (Baseline) |
Product | 6/2/14 | 5/25/15 | |
Requirements | 6/2/14 | 8/22/14 | 60,000.00 |
Design | 8/25/14 | 11/14/14 | 90,000.00 |
Build | 11/17/14 | 3/20/15 | 120,000.00 |
Test | 3/23/15 | 5/22/15 | 50,000.00 |
Release | 5/25/15 | 5/25/15 | 0.00 |
You have to report project status as of January 30, 2015. The associated schedule and cost information is provided below. Assume: (1) a five-day work week; and (2) a constant resource loading (i.e., the rate of planned expenditures is constant over the duration of each activity).
Actual
Activity Name | % Complete | Start (Actual) | Finish (Actual) | Cost (Actual) |
Product | 6/2/14 | NA | ||
Requirements | 100 | 6/2/14 | 8/30/14 | 68,000 |
Design | 100 | 8/31/14 | 11/20/14 | 85,000 |
Build | 70 | 11/21/14 | NA | 110,000 |
Test | 0 | NA | NA | 0 |
Release | 0 | NA | NA | 0 |
Show all work. Round dollar values to the nearest dollar. Calculate all other variables to three decimal places.
- Earned Value Measures
- Calculate earned value measures for each activity and for the cumulative project as of January 30, 2015; fill in the table below:
Activity | Planned Value (PV) | Earned Value (EV) | Actual Cost (AC) |
Requirements | 68,000 | ||
Design | 85,000 | ||
Build | 110,000 | ||
Test | 0 | ||
Release | 0 | ||
Entire Project |
- What is the Budget at Completion (BAC) for the project?
Financial Accounting Information For Decisions
ISBN: 978-0324672701
6th Edition
Authors: Robert w Ingram, Thomas L Albright