Question: Your Supervisor has requested to develop a Precedence Diagram (PDM) - AON network for a project using the information illustrated in the Table below (Hint:
Your Supervisor has requested to develop a Precedence Diagram (PDM) - AON network for a project using the information illustrated in the Table below (Hint: draw the Finish to Start relationships first). ID Duration Finish-to-Start Predecessor Finish-to-Start Lag Additional Lag Relationship Lag A 2 None 0 None 0 B 6 None 0 None 0 C 4 A 0 None 0 D 8 A,B 0 Start-Finish D to G 12 E 20 D C 0 10 Finish-Finish E to F 10 F 3 D 0 None 0 G 5 C,E 0 Start-Start G to H 8 H 10 C E 14 0 None 0 I 6 F,G,H 0 None 5 i. Draw the complete PDM network showing all the links with relevant lag factors and estimate ES, EF, LS, LF, and Total Float (TF) (8 marks) ii. Show the Critical Path and overall project time (2 marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
