Question: Your team has been assisting you with developing the project charter. The project involves replacing all the 1 6 computer monitors at the workstations

Your team has been assisting you with developing the project charter. The project involves replacing all the 16" computer monitors at the workstations in the office building with two 24" touch-screen monitors mounted on movable arms. One of your project team members points out that the work can only be carried out between 6 PM and 5 AM as the business must be operational during the day. Where would you put this statement in the project charter?
Risks
Issues
Assumptions
Constraints
 Your team has been assisting you with developing the project charter.