Question: Your team has come up with 4 3 4 risks and 1 6 major causes of those risks. The project is the last in a
Your team has come up with risks and major causes of those risks. The project is the last in a series of projects that the team has worked on together. The sponsor is very supportive, and a lot of time was invested in making sure the project work was completed and signed off by all key stakeholders. During project planning, the team cannot come up with an effective way to mitigate or insure against a risk. It is not work that can be outsourced, nor can it be deleted. What would be the BEST solution?
Question options:
Look for ways to accept the risk.
Accept the risk.
Look for ways to avoid the risk.
Continue to investigate ways to mitigate the risk.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
