Question: Your team has come up with 4 3 4 risks and 1 6 major causes of those risks. The project is the last in a
Your team has come up with risks and major causes of those risks. The project is the last in a series of projects that the team has worked on together. The owner is very supportive, and a lot of time was invested in making sure the project work was complete and signed off by all key stakeholders.
During project planning, the team cannot come up with an effective way to mitigate or insure against a risk. It is not work that can be outsourced, nor can it be deleted. What would be the BEST solution?
Group of answer choices
Look for ways to avoid the risk
Accept the risk
Continue to investigate ways to mitigate the risk
Look for ways to transfer the risk