Your team identified thirty risks on a project.

Your team identified thirty risks on a project. They then rated their likelihood of occurrence and their impact on the project. They used this information to prioritize these identified risks. What type of analysis does this represent? a) b) c) d) Qualitative Analysis Quantitative Analysis SWOT Analysis Risk Score Analysis