Question: Your team provides the following data on three process steps for each day of operations as follows: Available time per shift (seconds) 27,000 Shifts: 1

Your team provides the following data on three process steps for each day of operations as follows:

Available time per shift (seconds) 27,000 Shifts: 1 Daily Customer Demand Rate: 250 Takt Time (seconds): 108.0 Cycle Time (seconds) for step 1: 300.0 Cycle Time (seconds) for step 1: 400.0 Cycle Time (seconds) for step 1: 275.0 Queue Time Delay for step 1: 1 hour Queue Time Delay for step 1: 30 minutes Queue Time Delay for step 1: 2 hours Number of Units in WIP (Work-In-Process) waiting at step 1: 500 Number of Units in WIP (Work-In-Process) waiting at step 2: 400 Number of Units in WIP (Work-In-Process) waiting at step 3: 750 WIP (Work-In-Process) before step 1 (in days): 2 WIP (Work-In-Process) between step 1 and 2 (in days): 3 WIP (Work-In-Process) between step 2 and 3 (in days): 4 WIP (Work-In-Process) after step 3 before loading on the truck (in days): 1

What is the throughput time?

Group of answer choices

2.5 days

5 days

10 days

7.5 days

What is the throughput time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!