Question: You're given a three task linear sequence ( A - > B - > C ) task a takes eight minutes to perform, task B

You're given a three task linear sequence (A->B->C) task a takes eight minutes to perform, task B takes 12 minutes and task. C takes 10 minutes. Each task can process one customer at a time and there are no buffers between any of the stations. Suppose you could allocate some of the work that's being performed specifically suppose you can reduce the time each customer spend it by two minutes, but only by increasing the time each customer spends at by two minutes how would reallocating the work in this fashion impact the throughput rape that can flow out of task.