Question: You're going to install a system for a client you have contracted that installation and user training is completed within 17 days each day beyond

You're going to install a system for a client you have contracted that installation and user training is completed within 17 days each day beyond that will incur a $300 penalty. Create a crashing analysis in Excel to determine the best choice economically for implementation
8 days * Predecessor None None B,C Activity Duration Aget import license 10 days B shipping C train users in method 16 days D train on system 2 days You have options (*) for shipping (activity B): Slow boat 8 days Fast boat 7 days Bush airplane 5 days Normal airplane 3 days Chartered plane 1 day $100 $200 $400 $600 $900Step by Step Solution