Question: You're managing a complex project that involves multiple interdependent tasks. Some tasks have strict deadlines, while others have a bit more flexibility in terms of
You're managing a complex project that involves multiple interdependent tasks. Some tasks have strict deadlines, while others have a bit more flexibility in terms of timing.
In the context of project scheduling, which of the following terms refers to the amount of time an activity can be delayed without delaying the project's overall completion?
Question options:
Critical path
Schedule buffer
Free Float