Question: You're managing a project to install 2 0 0 windows in a new skyscraper and need to figure out your budget. Each week of the
You're managing a project to install windows in a new skyscraper and need to figure out your budget. Each week of the project costs the same: your team members are paid a total of $ every week, and yo need $ worth of parts each week to do the work. If the project is scheduled to last weeks, what's the BAC for the project?
BAC
What will the Planned Complete be four weeks into the project?
Planned Complete
This is the part that takes some Even though we are at th beginning of the project thinking How do you know what can still figure out what will be in four weeks.
What should the PV be four weeks into the project?
dotsdotsdotsdots