Question: You're tasked with organizing a large - scale charity event, which includes the following tasks, their durations, and their dependencies: Venue Booking ( A )

You're tasked with organizing a large-scale charity event, which includes the following tasks, their durations, and their dependencies:
Venue Booking (A): 2 days, no dependencies (immediate predecessors)
Vendor Selection (B)3 days, depends on A.
Marketing Campaig (C): 5 days, no dependencies.
Ticket Sales Setup (D): 2 days, depends on B and C
Event Programming (E): 4 days, depends on B
Final Preparations (F):3 days, depends on D and E.
Now you want to expedite the project by 2 days. Each task can be expedited by 1 day at the following additional costs:
Venue Booking (A): $350
Vendor Selection (B): $150
Marketing Campaign (C): $30
Ticket Sales Setup (D): $200
Event Programming (E): $300
Final Preparations (F): $100
What is the least expensive way to reduce the total event preparation time by 2 days, and what is the total additional cost?
 You're tasked with organizing a large-scale charity event, which includes the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!