You've been assigned to do the cost analysis for a proposal for sole source work of a
Fantastic news! We've Found the answer you've been seeking!
Question:
You've been assigned to do the cost analysis for a proposal for sole source work of a noncommercial nature and an estimated value of $5.4 million. When you reviewed the contractor's cost summary you noticed that the amount of other direct costs was $1.1 million which is approximately 20% of the total estimated value ($1.1 million/$5.4 million). Given this level of ODC's what action should you take?
Nothing since this is the contractor's responsibility.
Review and evaluate the contractor's proposal Basis of Estimate that makeup $1.1 million of ODC's.
Nothing since this is a minor amount.
Send the proposal to general council as a fraud alert.