Question: You've been tasked with identifying the early start and late start days for each presented activity. Table 1 . Schedule Information Do the following: Draw
You've been tasked with identifying the early start and late start days for each presented activity.
Table Schedule Information
Do the following:
Draw an AON schedule for the project as shown in Table
Perform forward pass and backward pass calculations to determine early and late dates for each activity.
Calculate the total and free floats for each activity.
What is the duration of the project in days?
Highlight the critical paths activities
Assume that no relationship between activities A and Recalculate the schedule. What is the revised duration
in days?
Assume that no relationship between activities and Recalculate the schedule. What is the revised duration in
days?
Assume that activity takes an additional days. Recalculate the schedule. What is the revised duration in days?
Assume that activity takes an additional days. Recalculate the schedule. What is the revised duration in
days?
Assume that activity takes an additional days. Recalculate the schedule. What is the revised duration in
days?
Table Legend
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock