Question: You've been tasked with identifying the early start and late start days for each presented activity. Table 1 . Schedule Information Do the following: Draw

You've been tasked with identifying the early start and late start days for each presented activity.
Table 1. Schedule Information
Do the following:
Draw an AON schedule for the project as shown in Table 1.
Perform forward pass and backward pass calculations to determine early and late dates for each activity.
Calculate the total and free floats for each activity.
What is the duration of the project in days?
Highlight the critical paths (activities).
Assume that no relationship between activities A and D. Recalculate the schedule. What is the revised duration
in days?
Assume that no relationship between activities F and J. Recalculate the schedule. What is the revised duration in
days?
Assume that activity E takes an additional 2 days. Recalculate the schedule. What is the revised duration in days?
Assume that activity D takes an additional 20 days. Recalculate the schedule. What is the revised duration in
days?
Assume that activity D takes an additional 30 days. Recalculate the schedule. What is the revised duration in
days?
Table 1. Legend
You've been tasked with identifying the early

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!