Question: Yun is using PERT / CPM to help her manage a project. All activities in this project have multiple interdependencies. The earliest start times for
Yun is using PERTCPM to help her manage a project. All activities in this project have multiple interdependencies. The earliest start times for each activity with preceding activities:
A Will be the largest finish time among preceding activities for each activity
B Can be shortened by beginning prior activities sooner if they have multiple interdependencies
C Can be calculated by starting from the last node and working backward
D Can be calculated by using the smallest value start time for all activities leaving an activity
E None of the above