Question: z Practice Problems 1 . 2 Consider the following project network and activity times ( in weeks ) : a . Identify the critical path.

z
Practice Problems 1.2
Consider the following project network and activity times (in weeks):
a. Identify the critical path.
b. How much time will be needed to
complete this project?
c. Can activity D be delayed without
delaying the entire project? If so2, by howe
many weeks?
d. Can activity C be delayed without
delaying the entire project? If so, by how
many weeks?
e. What is the schedule for activity E?