Question: z Practice Problems 1 . 2 Consider the following project network and activity times ( in weeks ) : a . Identify the critical path.
z
Practice Problems
Consider the following project network and activity times in weeks:
a Identify the critical path.
b How much time will be needed to
complete this project?
c Can activity D be delayed without
delaying the entire project? If by howe
many weeks?
d Can activity be delayed without
delaying the entire project? If so by how
many weeks?
e What is the schedule for activity