Question: ZAKI LLP is a networking entity. Required Using the data provided below Draw an A-O-A diagram based on normal times and identify the critical path,

ZAKI LLP is a networking entity.

Required

Using the data provided below

  1. Draw an A-O-A diagram based on normal times and identify the critical path, calculate the normal cost for the project.
  2. Determine the minimum project completion time with the least cost and calculate the percentage increase in costs.
  3. Use the network diagram in (a) above to construct a simple Gantt chart.

Note: Time is in Weeks and Cost in USD.

Activity Normal time Crash time Normal cost Crash cost
1-2 10 7 1,000 1,600
1-3 15 10 2,000 3,000
2-4 8 6 1,800 2,600
2-5 20 16 4,500 5,300
3-6 30 20 7,200 9.600
4-5 14 12 5,000 6,000
5-6 12 9 3,300 4,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!