Question: Implement the additional statistic-collection function described in Exercise 2-1, and add a plot that tracks the total number of parts in the system (also called
Implement the additional statistic-collection function described in Exercise 2-1, and add a plot that tracks the total number of parts in the system (also called work in process , abbreviated as WIP) over time. Note that at any given point in simulated time, WIP is the number in queue plus the number in service; you might also use the Expression Builder and check the Help topic EntitiesWIP Variable.