Question: In the Program Evaluation and Review Technique (PERT), we are interested in the total time to complete a project that is comprised of a large
In the Program Evaluation and Review Technique (PERT), we are interested in the total time to complete a project that is comprised of a large number of subprojects. For illustration, let X1, X2, X3 be three independent random times for three subprojects. If these subprojects are in series (the first one must be completed before the second starts, etc.), then we are interested in the sum Y = X1+X2+X3. If these are in parallel (can be worked on simultaneously), then we are interested in Z = max(X1, X2, X3). In the case each of these random variables has the uniform distribution with pdf f(x) = 1, 0 < x < 1, zero elsewhere, find (a) the pdf of Y and (b) the pdf of Z.
Step by Step Solution
3.35 Rating (164 Votes )
There are 3 Steps involved in it
a The pdf of Y X1X2X2 is given by fx 13x 131 x and the expected value of Y is EY ... View full answer