Question: Write a brief report comparing the sampling plans described in Exercises 21.9 and 21.12. Discuss the relative costs of the two plans and the frequency
Write a brief report comparing the sampling plans described in Exercises 21.9 and 21.12. Discuss the relative costs of the two plans and the frequency of Type I and Type II errors.
A production facility produces 100 units per hour and uses an x chart to monitor its quality. The control limits are set at 3 standard errors from the mean. When the process goes out of control, it usually shifts the mean by 1.5 standard deviations. Sampling is conducted once per hour with a sample size of 3.
Step by Step Solution
3.51 Rating (164 Votes )
There are 3 Steps involved in it
Sampling 3 units per hour means that on average we will produce ... View full answer