Question: In what process can a project manager determine which activities have the greatest potential impact on the project timeline if they are not completed on
In what process can a project manager determine which activities have the greatest potential impact on the project timeline if they are not completed on time?
a. Collect requirements and define the scope statement.
b. Create a WBS.
c. Define and sequence activities.
d. Estimate effort, duration, and resources.
e. Identify the critical path.