Question: 7. Chambers Inc. is considering using the PPB lot-sizing approach, but first it wants to compare the approach to its current lot-sizing method, EOQ. Chambers

7. Chambers Inc. is considering using the PPB lot-sizing approach, but first it wants to compare the approach to its current lot-sizing method, EOQ.

Chambers has selected a sample component for the comparison, and its requirements are given below. Ordering cost is $27 per order, and carrying cost is $0.25 per unit per period. (Use average inventory.) Using the sample component data, construct schedules using PBB and EOQ.

Also, compare the costs of these schedules.

Period 1 2 3 4 5 67 8 Requirements 51 14 59

Period 1 2 3 4 5 67 8 Requirements 51 14 59 93 44 12 67 60

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Supply Chain Management Questions!

Q:

a