My Mothers Closet Company solicited bids from several contractors to construct an addition to its office building.

Question:

My Mother’s Closet Company solicited bids from several contractors to construct an addition to its office building. The lowest bid received was for $375,000. My Mother’s Closet Company decided to construct the addition itself at a cost of $298,500. What amount should be recorded in the building account?