Question: 18. For that same network diagram below, what's the float for activity F? A. 0 weeks B. 2 weeks C. 4 weeks D. 5 weeks
18. For that same network diagram below, what's the float for activity F? A. 0 weeks B. 2 weeks C. 4 weeks D. 5 weeks

Start A 1 week B 2 weeks 2 E 2 weeks 3 weeks 5 G 2 weeks F 2 weeks 3 G 5 weeks 6 H 1 week End