Question: Using the data in the table from the previous problem: a. Create a table similar to the one in Figure 3.27 if you havent done

Using the data in the table from the previous problem:

a. Create a table similar to the one in Figure 3.27 if you haven’t done so already.

b. For Week 4, calculate the budget at completion (BAC), planned value (PV), actual cost (AC), and earned value (EV) at week 3.

c. For Week 4, calculate the performance measures of cost variance (CV), schedule variance (SV), the cost performance index (CPI), and the schedule performance index (SPI).

d. What can you say about the budget in Week 4 by using these performance measures?

e. What can you say about the schedule in Week 4 by using these performance measures?

f. For Week 4, calculate the estimated time to complete (ETC) and estimate at completion (EAC).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Systems Analysis And Design Questions!