You are the project manager of a medium-size project that is scheduled to take 10 months from

Question:

You are the project manager of a medium-size project that is scheduled to take 10 months from project initiation on September 1st through delivery on June 30th. It is now April 1st, seven months since the project began, and the project is slightly behind schedule, by perhaps a week.

Draw a Gantt chart (you may use the style shown in Figure 3-2 or another Gantt chart style if you prefer). Assume that project phases can overlap.

Data from Figure 3-2

image text in transcribed

Step by Step Answer:

Related Book For  answer-question

Introduction To Systems Analysis And Design

ISBN: 9780073402949

1st Edition

Authors: Jeffrey Whitten, Lonnie Bentley

Question Posted: