Question: 13. In an n-job, 3-machine sequencing problem, if the minimum times on the first and the third machines are both equal to or greater than
13. In an n-job, 3-machine sequencing problem, if the minimum times on the first and the third machines are both equal to or greater than the maximum time on the second machine, then the problem can be solved by a standard method.Mark the statement as T (True) or F (False).