Question: Solve the following assignment problem and obtain the minimum cost at which all the jobs can be performed. This problem is unbalanced since number of
Solve the following assignment problem and obtain the minimum cost at which all the jobs can be performed.

This problem is unbalanced since number of jobs is 5 while the number of workers is 4. We first balance it by introducing a dummy worker E, as shown in Table 6.18.

Job (Cost in '00 Rs) Worker 1 2 3 4 5 A 25 18 32 20 21 B 34 25 21 12 17 C D 22 20 17 20 32 16 20 28 20 20 16 27