Question: Suppose we modify the production model from Section 1.3 to obtain the following mathematical model: Max 10x s.t. ax 40 x 0 Where
Max 10x
s.t.
ax ≤ 40
x ≥ 0
Where a is the number of hours required for each unit produced. With a = 5, the optimal solution is x = 8. If we have a stochastic model with a = 3, a = 4, a = 5, or a = 6 as the possible values for the number of hours required per unit, what is the optimal value for x? What problems does this stochastic model cause?
Step by Step Solution
3.40 Rating (162 Votes )
There are 3 Steps involved in it
If a 3 x 13 13 and profit 133 If a 4 x 1... View full answer