Question: Susan Rogers project (see Problem 7-27) has progressed over the past several weeks, and it is now the end of week 8. Susan would like
Susan Rogers project (see Problem 7-27) has progressed over the past several weeks, and it is now the end of week 8. Susan would like to know the current status of the project with regard to schedule and budget by developing an appropriate table. Assume that all activities follow their earliest time schedules. The relevant data are shown in the following table.
.png)
PERCENTAGE COMPLETED 100 100 100 40 60 ACTUAL COST $1,900 5,300 $6,150 $1,800 $1,755 ACTIVITY