The Butterfield Company makes a variety of knives. Each knife is processed on four machines. The processing times required are as follows. Machine capacities (in hours) are 1,500 for machine 1; 1,400 for machine 2; 1.600 for machine 3; and 1,500 for machine 4.
Each product contains a different amount of two basic raw materials. Raw material 1 costs $0.50 per ounce, and raw material 2 costs $1.50 per ounce, there are 75,000 ounces of raw material 1 and 100,000 ounces of raw material 2 available.
a. If the objective is to maximize profit specify the objective function and constraints for the problem. Assume that labor costs are negligible.
b. Solve the problem with a computerpackage.