The delivered-equipment cost for setting up a production and assembly line for high-sensitivity, gas-damped accelerometers is $650,000.

Question:

The delivered-equipment cost for setting up a production and assembly line for high-sensitivity, gas-damped accelerometers is $650,000. If the direct cost and indirect cost factors are 1.82 and 0.31, respectively, and both factors apply to delivered-equipment cost, the total plant cost estimate is approximately:
(a) $2,034,500
(b) $1,734,500
(c) $1,384,500
(d) $1,183,000