Question: The end product J is made from components K, and L. K is made from M, N, and O. (a) What is the replenishment lead
(a) What is the replenishment lead time for J, assuming there are no inventories?
(b) Calculate the gross requirements for each of the components if the company plans to build 10 of its J model. Assume that there are no beginning inventories.
(c) Calculate the gross requirements for each of the components if the company plans to build 10 of its J model if you have these beginning inventories: 20 K and 80 M.
(d) What is the replenishment lead time if the company plans to build 10 of its J model, assuming the beginning inventories given in (c) above?
Step by Step Solution
3.40 Rating (162 Votes )
There are 3 Steps involved in it
a 7 weeks b 10 J 40 ... View full answer