Question: The following information is available for a particular consulting contract performed by Newland Business Consultants in 2012: Consulting labor costs . . . . .
The following information is available for a particular consulting contract performed by Newland Business Consultants in 2012:
Consulting labor costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $4,000
Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 500
Overhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ?
Total cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ ?
Newland applies overhead on the basis of client consulting hours. The estimated total overhead costs for 2012 are $6.2 million, and the estimated total consulting hours are 150,000. Newland pays its consultants $40 per hour.
1. Compute the predetermined overhead rate.
2. What are the allocated overhead cost and the total cost of this particular contract?
Step by Step Solution
3.34 Rating (163 Votes )
There are 3 Steps involved in it
1 Overhead rate 62 million 150000 hours 4... View full answer