Question: The following list presents specific project activities and their scheduled starting and completion times: a. Using a format similar to that in Figure 18-3, prepare
The following list presents specific project activities and their scheduled starting and completion times:
.png)
a. Using a format similar to that in Figure 18-3, prepare a Gantt chart for this project. Assume that each activity starts on a Monday and ends on a Friday.
b. Assume today is February 16 and activities A and B have been completed, C is half completed, F is a quarter completed, and the other activities have not yet commenced. Record this information on your Gantt chart. Is the project behind schedule, on schedule, or ahead of schedule? Explain.
c. Discuss the relative merits of the Gantt chart and PERT as project planning and controltools.
ACTIVITY STARTING DATE ENDING DATE an. Jan Jan. 26 Mar. 2 Mar. 2 Feb. 2 Mar. 30 Mar. 23 Feb. 9 Jan. 19 Feb. 23 Mar 23 Mar. 16 Mar. 16 Apr. 20 Apr. 27
Step by Step Solution
3.37 Rating (172 Votes )
There are 3 Steps involved in it
a Project Planning Chart b Partially Completed Gantt chart Once the activity bars have been filled i... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
373-B-A-I-S (5074).docx
120 KBs Word File
