Question: The following represents a project that should be scheduled using CPM: a. Draw the network. b. What is the critical path? c. What is the
.png)
a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?
Times (days) Immediate Predecessors am Activity A 2 3 B 1 2 3 3 4 11 4 c,d G d,e 4 6. f,g 2 4 4. 3. 2. 3. 3.
Step by Step Solution
3.40 Rating (156 Votes )
There are 3 Steps involved in it
The mentioned data is shown as below Times days Activity Immediate Predecessors a m b A 1 3 5 B 1 2 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1019-B-C-F-D-F(405).docx
120 KBs Word File