Question: The information below was taken from the job cost sheets of Bates Company. During July, jobs no. 103 and 104 were completed, and jobs no.
.png)
During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. From this information, compute the following:
a. The work in process inventory at June 30.
b. The finished goods inventory at June 30.
c. The cost of goods sold during July.
d. The work in process inventory at July 31.
e. The finished goods inventory at July31.
Manufacturing Costs as of June 30 Job Number 101 102 103 104 105 106 Manufacturing Costs in July $4,200 3,240 900 $2,000 4,000 6,000 3,700 2,250
Step by Step Solution
3.50 Rating (150 Votes )
There are 3 Steps involved in it
a 3150 900 2250 jobs no 103 and 104 ... View full answer