The Operations Analyst for a company is studying the inventory stocking policy for a product (#A123). His

Question:

The Operations Analyst for a company is studying the inventory stocking policy for a product (#A123). His records show that the demand per day is normally distributed with a mean of 210 and a standard deviation of demand of 5. Lead time is 4 days. The current reorder point is 860.
A) Compute the probability of stock out for the current reorder point.
B) The analyst has just been informed that the (above) standard deviation of daily demand was computed incorrectly. The corrected standard deviation is 7.07. What would be the correct reorder point be in order to retain the same probability of stock out (as in part (a))?
C) The analyst has some new information. His clerk has informed him that the lead time has changed to 5 days. What would the new reorder point be if the allowed probability of stock out is still the same as before?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managing Business Process Flows Principles of Operations Management

ISBN: 978-0136036371

3rd edition

Authors: Ravi Anupindi, Sunil Chopra, Sudhakar Deshmukh, Jan Van Mieg