The Rushing Construction Company obtained a construction contract to build a highway and bridge over the Snake

Question:

The Rushing Construction Company obtained a construction contract to build a highway and bridge over the Snake River. It was estimated at the beginning of the contract that it would take three years to complete the project at an expected cost of $50,000,000. The contract price was $60,000,000. The project actually took four years, being accepted as completed late in 2014. The following information describes the status of the job at the close of production each year.
The Rushing Construction Company obtained a construction contract to build

Instructions:
1. What is the revenue, cost, and gross profit recognized for each of the years 2011-2015 under (a) the percentage-of-completion method and (b) the completed-contract method?
2. Give the journal entries for each year assuming that the percentage-of-completion method is used.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question

Intermediate Accounting

ISBN: 978-0538479738

18th edition

Authors: Earl K. Stice, James D. Stice

Question Posted: