Question: The Rushing Construction Company obtained a construction contract to build a highway and bridge over the Snake River. It was estimated at the beginning of
.png)
Instructions:
1. What is the revenue, cost, and gross profit recognized for each of the years 2011-2015 under (a) the percentage-of-completion method and (b) the completed-contract method?
2. Give the journal entries for each year assuming that the percentage-of-completion method is used.
2011 2012 2013 kilA! 2015 Actual cost incurred $12,000,000 $18,160,000 $14,840,000 $10,000,000 0 0 0 0
Step by Step Solution
3.42 Rating (187 Votes )
There are 3 Steps involved in it
1 a 2011 2012 2013 2014 1 Contract price 60000000 60000000 60000000 60000000 2 Actual cost incurred ... View full answer