Question: The time required to complete a certain type of construction project follows a normal distribution with a mean of 60 weeks and a standard deviation

The time required to complete a certain type of construction project follows a normal distribution with a mean of 60 weeks and a standard deviation of 4 weeks. What is the probability of completing the project in no more than 60 weeks? 