Question: The time to complete a construction project is normally distributed with a mean of 60 weeks and a standard deviation of 4 weeks. (a) What
The time to complete a construction project is normally distributed with a mean of 60 weeks and a standard deviation of 4 weeks.
(a) What is the probability the project will be finished in 62 weeks or less?
(b) What is the probability the project will be finished in 66 weeks or less?
(c) What is the probability the project will take longer than 65 weeks?
Step by Step Solution
3.39 Rating (168 Votes )
There are 3 Steps involved in it
The time to complete the project X is normally distribute... View full answer