Question: There is an 82% chance the project below can be completed in X weeks or less. What is X? MoST OPTIMISTICLIKELY PESSIMISTIC MosT MosT ACTIVITY
There is an 82% chance the project below can be completed in X weeks or less. What is X?
.png)
MoST OPTIMISTICLIKELY PESSIMISTIC MosT MosT ACTIVITY 10 10 4
Step by Step Solution
3.31 Rating (163 Votes )
There are 3 Steps involved in it
Activity a m b Expected time Variance A 2 5 11 55 225 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
68-B-M-A-A-B-C (842).xlsx