Question: There is an 82% chance the project below can be completed in X weeks or less. What is X? MoST OPTIMISTICLIKELY PESSIMISTIC MosT MosT ACTIVITY

There is an 82% chance the project below can be completed in X weeks or less. What is X?

There is an 82% chance the project below can be

MoST OPTIMISTICLIKELY PESSIMISTIC MosT MosT ACTIVITY 10 10 4

Step by Step Solution

3.31 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Activity a m b Expected time Variance A 2 5 11 55 225 ... View full answer