Question: This continues the Daniels Consulting situation from Problem P22-57 of Chapter 22. Assume Daniels has created a standard cost card for each job. Standard direct
This continues the Daniels Consulting situation from Problem P22-57 of Chapter 22. Assume Daniels has created a standard cost card for each job. Standard direct materials per job include 10 software packages at a cost of $900 per package. Standard direct labor costs per job include 105 hours at $100 per hour. Daniels plans on completing 12 jobs during March 2018.
Actual direct materials costs for March included 90 software packages at a total cost of $81,450. Actual direct labor costs included 110 hours per job at an average rate of $107 per hour. Daniels completed all 12 jobs in March.
Requirements
1. Calculate direct materials cost and efficiency variances.
2. Calculate direct labor cost and efficiency variances.
Step by Step Solution
3.60 Rating (171 Votes )
There are 3 Steps involved in it
Requirement 1 Direct Materials Cost Variance ACSC AQ 905 p... View full answer