Question: Three projects have the cash flows given here. The cost of capital is 10%. a. Calculate the paybacks for all three projects. Rank the projects
Three projects have the cash flows given here. The cost of capital is 10%.
a. Calculate the paybacks for all three projects. Rank the projects from best to worst based on their paybacks.
b. Calculate the NPVs for all three projects. Rank the projects from best to worst based on their NPVs.
c. Why are these two sets of rankingsdifferent?
.png)
YEAR Project 1- Project 2- Project 3- 10 4 321 5 10 1 23 4 5 10 4 32 10
Step by Step Solution
3.57 Rating (168 Votes )
There are 3 Steps involved in it
a Project 1 Project 2 Project 3 Years Cash Flows Cummulative Cash Flows Cummulative Cash Flows Cummu... View full answer