Question: Turow Trailers assembles horse trailers. Two models are manufactured: G7 and V8. While labor-intensive, the production process is not very complicated. The single plant produces

Turow Trailers assembles horse trailers. Two models are manufactured: G7 and V8. While labor-intensive, the production process is not very complicated. The single plant produces all the trailers with 48 work teams of two or three workers. Sixteen supervisors oversee the work teams. Materials handlers deliver all the parts needed for each trailer to the work team. Human resources, accounting, inspection, purchasing, and tools are the other major overhead departments. Some operating statistics for 2010 and 2011 follow.


Turow Trailers assembles horse trailers. Two models are manufactured: G7



Required:
a. Calculate all the overhead variances for both 2010 and 2011.
b. Discuss who in the plant should be held responsible for each overheadvariance.

2010 2011 Budgeted denominator volume (direct labor hours) Flexible budget: l million I million Fixed overhead Variable overhead per direct lubor hour $2.1 million $7 $2.2 milliorn 58 Units prodoced: 07 V8 11.000 12.000 8,000 6,000 Standard direct bbor hours per unit of 67 40 50 $9.0 million I million 40 50 $8.1 milliotn 0.7 million Actual overbead incurred Actual direct labor hours

Step by Step Solution

3.43 Rating (178 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

2010 2011 a Overhead rate flexible budget expected volume 2171 m 9100000 2281 m 10200000 denominator ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

364-B-M-A-D-M (2067).docx

120 KBs Word File

Students Have Also Explored These Related Managerial Accounting Questions!