Question: Two different routes, which entail driving across a mountainous section, are being considered for a highway construction project. The first route (the high road) will
.png)
The High The Low $200,000 $450,000 10 Road Road Average consuruction c per mile Number of miles required Annual benefit per car per 35 S0015 $0.045 mile Annual O&M cosLs perile $2000 $10,000