Question: Two sites are being considered for wind power generation. In the first site, the wind blows steadily at 7 m/s for 3000 hours per year,

Two sites are being considered for wind power generation. In the first site, the wind blows steadily at 7 m/s for 3000 hours per year, whereas in the second site the wind blows at 10 m/s for 2000 hours per year. Assuming the wind velocity is negligible at other times for simplicity determines which a better site is for wind power generation. Hint: Note that the mass flow rate of air is proportional to wind velocity.