Question: Upon completing a job, direct materials totaled $3,000; direct labor, $3,500; and factory overhead, $1,500. Units produced totaled 1,000. What is the per unit cost?

Upon completing a job, direct materials totaled $3,000; direct labor, $3,500; and factory overhead, $1,500. Units produced totaled 1,000. What is the per unit cost?
Select one:
a. $8,000
b. $6,500
c. $6.50
d. $8

Step by Step Solution

3.51 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Per unit ... View full answer